Tesla Shanghai has received a license! First case outside the United States

The China (Shanghai) Pilot Free Trade Zone Lingang New Area Management Committee (hereinafter referred to as the \”Shanghai Lingang Management Committee\”) announced on Monday (13th) that the Tesla (TSLA-US) Shanghai Energy Storage Gigafactory construction project has been completed License issuance.

The China (Shanghai) Pilot Free Trade Zone Lingang New Area Management Committee (hereinafter referred to as the \”Shanghai Lingang Management Committee\”) announced on Monday (13th) that the Tesla (TSLA-US) Shanghai Energy Storage Gigafactory construction project has completed the construction permit Certificate issued.
According to the \”Daily Economic News\” report, the Shanghai Lingang Management Committee stated that Tesla\’s Shanghai Energy Storage Gigafactory will produce ultra-large commercial energy storage batteries (Megapack) to help grid operators, utility companies, etc. store and distribute regeneration more efficiently. energy.
More than 200 ultra-large commercial energy storage batteries can form an energy storage power plant to store 1 million kilowatt hours of electricity.
The Tesla Energy Storage Gigafactory covers a total area of ​​approximately 200,000 square meters and is adjacent to the Tesla Shanghai Gigafactory. The total investment is approximately RMB 1.45 billion. This is Tesla’s first energy storage Gigafactory project outside the United States.
Tesla’s layout can be traced back to a year ago.
On April 9, 2023, Tesla signed a contract with the Lingang New Area on the Tesla Energy Storage Gigafactory project.
On December 22 of that year, Tesla held a land signing ceremony with the Lingang New Area Management Committee in Shanghai to announce the launch of the Tesla Energy Storage Gigafactory project.
According to \”Xinhua News Agency\”, Min Zhiguang, deputy director of the Lingang New Area Approval and Review Center and head of the Project Construction Service Office, said that the Tesla Shanghai Energy Storage Super Factory project applied the \”project service package\” newly launched by the Lingang New Area in the field of engineering construction. In other words, based on the project perspective and specific scenarios, a full set of service systems are pre-embedded before the start of approval, and all enterprise-side and government-side matters are stuffed into a \”package\” to formulate a node flow chart starting from the project.
\”Through the design of service packages, companies can quickly obtain relatively accurate and comprehensive government service requirements and management requirements from the earliest time when investment intentions are not completely clear, achieving a seamless connection throughout the entire process.
Especially when encountering problems, we don’t need to look for them separately in this department or that department. Instead, we have a relatively mature “zero-day” response and problem-solving mechanism.
\”Min Zhiguang said.
Tesla\’s Shanghai Energy Storage Gigafactory will plan to produce 10,000 commercial energy storage batteries per year at the initial stage of mass production in the first quarter of 2025, with an energy storage scale of nearly 40 GWh.
Data from the Advanced Industrial Research Institute (GGII) shows that China\’s energy storage lithium battery shipments in 2022 will be 130 GWh, which means that the production capacity of Tesla\’s super energy storage factory is equivalent to China\’s 2022 energy storage lithium battery shipments. one third.